• Home Page
  • CALL TO ACTION
    • THE LATEST
    • Industry Insights
    • Past Updates
    • Press Releases
  • Save Potterne Park Farm
    • The Case Against
    • The Proposal ....Exposed
    • Important Documents
    • Map
    • Impacts Montage
    • Gallery
  • One Tree Hill NOW REFUSED
    • Decision Notice
    • The Case Against
    • The Proposal ....Exposed
    • Important Documents
    • Map
    • Gallery
  • Donate
  • Contact us
  • More
    • Home Page
    • CALL TO ACTION
      • THE LATEST
      • Industry Insights
      • Past Updates
      • Press Releases
    • Save Potterne Park Farm
      • The Case Against
      • The Proposal ....Exposed
      • Important Documents
      • Map
      • Impacts Montage
      • Gallery
    • One Tree Hill NOW REFUSED
      • Decision Notice
      • The Case Against
      • The Proposal ....Exposed
      • Important Documents
      • Map
      • Gallery
    • Donate
    • Contact us
  • Home Page
  • CALL TO ACTION
    • THE LATEST
    • Industry Insights
    • Past Updates
    • Press Releases
  • Save Potterne Park Farm
    • The Case Against
    • The Proposal ....Exposed
    • Important Documents
    • Map
    • Impacts Montage
    • Gallery
  • One Tree Hill NOW REFUSED
    • Decision Notice
    • The Case Against
    • The Proposal ....Exposed
    • Important Documents
    • Map
    • Gallery
  • Donate
  • Contact us

STATUS (Sep 2026)

On July 1st 2025 the Strategic Planning Committee refused Potterne Park Farm's solar application. They refused on grounds of archaeology surveys not having been done, as recommended by the case officer. In addition, they extended the refusal to include Landscape and non compliance with the Potterne Neighbourhood Plan as grounds for refusal. See download link to Decision Notice below.


Group protesting against solar rooftops on farmland.

On September 8th 2025 an archaeological dig commenced at Potterne Park Farm - obviously connected to one of the planning refusal notifications for the solar farm application (see photo taken from PRoW EAST12). The applicant subsequently submitted an appeal against the decision to refuse the solar farm project at Potterne Park Farm.


PSAG submitted a weighty documentation set related to PPF Solar to the inspector. It included independent experts all saying solar on this site is against policy and not acceptable from a landscape, ecology and access point of view.  It also included evidence from the EA Register that this site will not get connected to the grid until Nov 2037 so we could be living with 11 years of uncertainty and sterilised land.


In April 2026 the Planning Inspector allowed the appeal, approving the Potterne Park solar farm despite overwhelming local opposition and serious, evidence-based concerns.


The decision relied heavily on uncertain future benefits, even though there is no confirmed grid connection (potentially not until 2037) and no requirement for the scheme to actually deliver electricity within any defined timeframe.


PSAG expert evidence — including clear deficiencies in ecological surveys (notably for rare protected bats), landscape harm, and fundamental questions over whether the scheme can even be delivered as proposed — was presented in full but ultimately dismissed or downplayed.



Following the appeal decision, and after extensive consultation with our legal team, PSAG filed a Judicial Review claim. The challenge focuses on the treatment of grid connection timing and its impact on the planning balance, and the permanent (not temporary) nature of the substation.


Unfortunately the Judicial Review has recently concluded without overturning the planning permission for Potterne Park Farm Solar.


Following the High Court's refusal of permission for the Judicial Review, PSAG considered seeking an oral renewal. However, the Court did not grant the Aarhus costs protection that would have limited liability for the other parties’ costs. PSAG's KC advised that an oral renewal remained arguable, but that the prospects of success were marginal. PSAG could not responsibly expose the campaign and its supporters to potentially significant further costs and therefore decided not to pursue the Judicial Review any further.


That is deeply disappointing, but it does not mean that the development is ready to proceed. Important pre-commencement conditions remain outstanding.


PPF obtained permission at appeal on a specific case:

  • a grid connection considerably earlier than November 2037 was accepted as possible and plausible;
  • the highway effects were assessed against a six-week construction scenario; and
  • planning permission was granted without delay, with development required to commence within three years.


No earlier grid-connection date was identified or evidenced before the Inspector. The judge concluded that it was not unlawful for the Inspector to treat the published November 2037 date as having been superseded by a “newer, albeit unspecific, calendar”—but no replacement date was identified.


PPF’s connection remains dependent upon reinforcement of the Melksham grid supply point. The NESO Existing Agreements Register, published as part of the connections-reform process, records 15 November 2037. Unless PPF secures a confirmed Gate 2 connection materially earlier than November 2037, the Inspector’s expectation of early renewable-energy benefits will not be delivered, leaving a development that incurs substantial commencement and environmental costs many years before generating any electricity.


Construction traffic and commencement


Condition 9 requires a detailed Construction Traffic Management Plan to be approved before any development or associated deliveries begin. It must cover vehicle numbers and frequency, the construction programme, delivery routes, access, holding areas and traffic-management measures.

Paragraph 45 of the appeal decision expressly records that the CTMP set out a six-week construction period. It was on the basis of that period and the accompanying mitigation measures that the Inspector concluded the development would not cause unacceptable or severe highway impacts. Condition 9 requires a final detailed CTMP, and any material departure from that scenario must be properly evidenced and assessed against the basis of the Inspector’s conclusion.

A token commencement would itself trigger substantial obligations and costs. Before development could begin, the developer would need approval of the CTMP and the environmental, ecological, drainage, highway and landscaping plans. Once development commenced, the approved landscaping would have to be planted in the first planting season and maintained thereafter. Those costs could arise many years before the development received any income from exporting electricity.


There is also a separate and unresolved private-law challenge concerning the proposed use of Potterne Park Lane. Neighbouring property owners claiming established rights over the lane have formally notified the developer and Wiltshire Council. Planning permission does not override private property rights.


PSAG will scrutinise the discharge of conditions against the case presented at appeal and hold Wiltshire Council to account for ensuring that it is not materially rewritten. Where justified, we will use the appropriate planning and legal avenues to ensure that the conditions are properly enforced.


PSAG thanks all the residents, supporters, experts and local councillors who have contributed their time, expertise and donations. Without that extraordinary community support, it would not have been possible to mount such a robust challenge.


This phase of legal proceedings may be over, but the campaign to protect Potterne and the Stert Valley is not.




Refusal of full planning permission

Decision Notice - 3rd July 2025 (pdf)

Download

Increasing Visibility 


Signs and Banners are being rolled out across villages.  If you have a useful vantage point and want to help, do contact us and stick a sign on your fence or in a window. Remember you need permission of the landowner and do not put your sign up on council land or telegraph poles and road signs. If you need any help putting a sign up, please contact us!


We are keeping our MP Brian Matthew fully informed of developments as well as our councillors Dominic Muns and Tamara Reay 

Potterne Solar Action Group – Game plan

We are expecting a long campaign


We will fight these applications every step of the way. We are raising funds, lobbying decision makers and showing the local community that we care.


We have a number of local experts who have given their time and expertise to refute the applicants’ claims, and you can see some of those responses under our documents tab or on the planning portal.


This is a special valley and it needs protection. The wildlife needs us to speak up for it because it cannot speak up for itself. Many of these species are legally protected and we will use that legal protection if anyone attempts to damage their environment.


YOUR HELP


We have great support from many people – over 1,100 people signed our petition seeking to protect this valley and oppose these two solar farms. If you think you can help, contact us. Get one of our signs and stick it on your fence, for example. 

Save One Tree Hill - The Case AgainstSave Potterne Park Farm - The Case Against
Contact us
Donate

COPYRIGHT © 2024 STOP POTTERNE SOLAR - ALL RIGHTS RESERVED.

  • Home Page

This website uses cookies.

We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.

DeclineAccept